Keras flags delay to new Diamond Creek processing plant

By Josh White

Date: Monday 29 Mar 2021

LONDON (ShareCast) - (Sharecast News) - Mineral resource company Keras Resources reported progress at the Diamond Creek high-grade direct shipping ore organic phosphate mine in Utah on Monday, reporting "encouraging results" from the marketing campaign over the winter.
The AIM-traded firm's 51% subsidiary Falcon Isle Holdings is the owner of Diamond Creek.

It said the results from the Falcon Isle marketing campaign over the winter period had reinforced management's confidence that 2021 sales targets would be met.

Covid-19 travel restrictions, which prevented the plant manufacturer's engineer to be on site during construction, had slowed the construction timeline, however, with the new processing plant now set to be commissioned in the second quarter.

Keras said that, due to the "significant demand" for both milled and granulated product, Falcon Isle had extended its third-party toll treating agreements to ensure that product was available during the final stage of the plant construction.

The increase in run-of-mine production during the 2020 mining campaign had ensured that there was sufficient plant feed until mining resumes in the spring, the board confirmed.

Once installed, the increased plant capacity and the expected associated economies of scale would reduce the unit cost and bolster margins going forward, it added.

"The trip to Togo and Utah has been extremely constructive and has proved how important face-to-face management interaction is in our industry," said chief executive officer Russell Lamming.

"Notwithstanding the significant impact that the pandemic has had, our US team has done a great job in both maintaining operational output and building value at the Diamond Creek operation."

Lamming said that despite the "short delay" in the commissioning timetable, the firm's management believed sales targets of 10,000 tons for 2021 were still achievable.

"The demand for our range of products has been very encouraging and we are looking forward to a very busy period as we move into spring and the recommencement of mining operations.

"We look forward to delivering further news regarding the commissioning of the processing plant and our 2021 production schedule in due course."

At 1300 GMT, shares in Keras Resources were down 3.67% at 0.12p.

Email this article to a friend

or share it with one of these popular networks:


Note 1: Prices and trades are provided by Digital Look Corporate Solutions and are delayed by at least 15 minutes.

 

KRS Market Data

Currency UK Pounds
Share Price 1.65p
Change Today -0.050p
% Change -2.94 %
52 Week High 5.20p
52 Week Low 1.50p
Volume 300,680
Shares Issued 80.50m
Market Cap £1.33m

KRS Star Ratings

Compare performance with the sector and the market.
more star ratings
Key: vs Market vs Sector
Value Not Available
Price Trend
93.57% below the market average93.57% below the market average93.57% below the market average93.57% below the market average93.57% below the market average
89.47% below the sector average89.47% below the sector average89.47% below the sector average89.47% below the sector average89.47% below the sector average
Income Not Available
Growth
21.28% above the market average21.28% above the market average21.28% above the market average21.28% above the market average21.28% above the market average
42.86% above the sector average42.86% above the sector average42.86% above the sector average42.86% above the sector average42.86% above the sector average

KRS Dividends

No dividends found

Trades for 26-Apr-2024

Time Volume / Share Price
14:05 70,000 @ 1.58p
11:38 7,572 @ 1.58p
10:09 3,108 @ 1.75p
09:26 110,000 @ 1.50p
09:26 110,000 @ 1.50p

Top of Page