LONDON (ShareCast) - (Sharecast News) - 88 Energy updated the market on its oil and gas operations on the North Slope of Alaska on Monday, reporting that ice road construction for the Winx-1 exploration well had now commenced.
The AIM-traded firm said the permit-to-drill for Winx-1 had also been submitted, with spud scheduled for mid-to-late February.
It explained that construction of the 11 mile ice road to the Winx-1 exploration well location started on 2 January, as planned.
"The ice road will take approximately three weeks to complete, ahead of construction of the ice pad upon which Nordic Rig#3 will be located for the drilling of Winx-1," the board said in its statement.
It also confirmed that the permit-to-drill for Winx-1 was submitted to the Alaska Oil and Gas Conservation Commission (AOGCC) on schedule, prior to the end of calendar year 2018.
"All logistics and permitting remains on schedule for a mid-late February spud date.
"Additional details related to the drilling and testing program will be released in due course."
88 Energy said Winx-1 as located around four miles east of the Horseshoe-1/1A well, which "significantly extended" the successful Nanushuk play fairway to the south.
"Winx-1 will target gross best estimate prospective resource of 400 million barrels of oil - 144 million barrels net to 88 Energy - across multiple stacked objectives, including the Nanushuk, which is the primary target of the well."
Email this article to a friend
or share it with one of these popular networks:
Currency | UK Pounds |
Share Price | 0.16p |
Change Today | 0.000p |
% Change | 0.00 % |
52 Week High | 0.43p |
52 Week Low | 0.15p |
Volume | 24,593,496 |
Shares Issued | 28,893m |
Market Cap | £45.51m |
Value |
---|
Price Trend |
---|
Income |
---|
Growth |
---|
No dividends found |
Time | Volume / Share Price |
16:38 | 3,800,000 @ 0.16p |
15:46 | 150,000 @ 0.16p |
15:26 | 63,853 @ 0.16p |
14:56 | 45,000 @ 0.16p |
14:54 | 1,259 @ 0.16p |
You are here: research