By Josh White
Date: Thursday 05 Jan 2017
LONDON (ShareCast) - (ShareCast News) - Africa and Europe-focused upstream gas company Sound Energy updated the market on its Badile project on Thursday, confirming that ground works at the well site were now complete.
The AIM-traded firm also said the conductor pipe was set last week, and the 3000 HP EMSCO C3 rig - owned by Pergemine - has been mobilised.
It said the mobilisation and rig-up operations were expected to be completed by the end of February, enabling drilling to commence during March.
"The Badile exploration well is planned to be drilled to a total depth of 4,600m to test the hydrocarbon potential of the Lower Jurassic Conchodon Dolomite with an independently assessed 100% unrisked best case estimate of 178 Bscfe, an upside high case in excess of 670 Bscfe and low case of 46 Bscfe," Sound Energy's board explained.
Email this article to a friend
or share it with one of these popular networks:
Currency | UK Pounds |
Share Price | 1.02p |
Change Today | 0.081p |
% Change | 8.63 % |
52 Week High | 1.93p |
52 Week Low | 0.64p |
Volume | 4,494,238 |
Shares Issued | 1,993.12m |
Market Cap | £20.33m |
RiskGrade | 409 |
Value |
---|
Price Trend |
---|
Income |
---|
Growth |
---|
No dividends found |
Time | Volume / Share Price |
15:55 | 100,000 @ 1.02p |
15:53 | 120,000 @ 1.04p |
15:45 | 250,000 @ 1.04p |
15:44 | 50,000 @ 1.04p |
15:31 | 726 @ 1.01p |
You are here: research